The objective of this
program is to conduct research that will lead to safer, more
economical pipeline construction, cost effective mechanised
welding and improved on-line quality control. This in turn should
lead to reduced danger to the public, reduced pipeline costs
and hence reduced greenhouse gas emissions and reduced dependence
on decreasingly available skilled welders.
These objectives will be achieved through the completion of
the following projects:
In-service welding of high pressure gas pipelines
The aim of this project has been to develop procedures for the
safe and effective in-service welding of high pressure, thin
walled, high strength steel, gas pipelines. The establishment
of guidelines for welding on thin walled high strength steel
pipelines will reduce time consuming weld procedure development
and enhance the economic expansion of pipeline networks by avoiding
the costly and inconvenient option of pipeline decommissioning.
The refinement of numerical models and increase in their scientific
credibility will provide direct industry benefits and enhance
Australian pipeline expertise. The application of advanced numerical
process models to determine suitable in-service welding procedures
for thin, high strength, gas pipelines is a novel process and
is leading to the consideration of alternative welding processes
to those conventionally used by the industry.
The two substantial issues during welding on in-service pipelines
are the risk of weld failure through cracking and the risk of
penetrating the pipe, a problem referred to as burn-through.
Controlling the heat input is a major concern.
The project work has developed computerised 3D simulations
of in-service welding using a commercial finite element code.
A new heat source formulation has been developed which extends
the concept of the double ellipsoidal heat source and allows
the approximation of weaving and welding angle. A new method
of burn-through assessment has been developed which improves
existing methods since it accounts for internal pipe pressure
and welding direction, which the current method does not do.
A 'user database' concept has been developed which may lead
to Windows based software that could easily be used to transfer
the technology developed in this project into an industrially
useful tool.
Experimental studies of in-service welding with low-hydrogen
electrodes have been carried out and the numerical predictions
have been verified by comparing predictions with measurements
made on an operational flow-loop.
Mechanised girth welds for thin walled pipes
During the 98/99 year the GMAW system which was previously found
to be viable was further developed and complete circumferential
pipe welds were made using solid wire consumables which matched
the properties of the X80 pipe material. It was shown that a
procedure combining a controlled short circuit transfer root
run with a pulsed GMAW fill gave good operating tolerance and
satisfactory joint properties. An on-line procedure control
and monitoring system was also built and this was evaluated
during laboratory trials and during field tests with in service
welding. The monitoring hardware/software package has been commercialised
and made available via an SME; Emtech Ltd. Work on a welding
system design has continued at the University of Adelaide and
a novel design concept has been developed; this system will
be taken to the prototype stage for evaluation. Work on an integrated
control and field welding QA system has commenced with the award
of an APA-I studentship to the University of Wollongong.
Electrical resistance welding of high strength linepipe
BHP Oil & Gas in conjunction with BHP Flat Products has
developed high strength pipe grades to meet the needs of the
Australian pipeline industry which is currently in a mode of
rapid expansion. The domestic supply of pipe to the rapidly
expanding pipeline network system is currently under threat
by imported pipe that is claimed to possess superior quality
in terms of weld zone fracture toughness.
To meet the stringent requirements now demanded of pipeline
operators the Centre has been working closing with BHP to identify,
monitor and control the process parameters known to influence
the occurrence of weld line imperfections.
Modified processing parameters and heat treatment conditions
in conjunction with on-line welding monitors have resulted in
significant improvements in pipe mill yields. This work has
been instrumental in the success of BHP O&G securing supply
of pipe for the Eastern Gas Pipeline which will run from Longford
in Victoria to Sydney. This technology will also benefit lower
grade products in terms of overall quality, production rate
and ultimately pipe price.
Quality monitoring of automated gas metal arc welding
To ensure acceptable quality of GMA welding for transmission
pipelines generally requires costly and time-consuming post
weld assessment and non-destructive examination (NDE). A distributed
on line monitoring system for a mechanised pipeline girth welding
system could be used instead and is currently being developed.
Both local area networks and internet technologies are being
evaluated for monitoring multi head field pipe welding systems,
with a specific emphasis on automated pipe welding systems.
Of crucial importance for the successful application of automated
GMAW systems for field pipe welding is that the standoff (contact
tip to workpiece distance) remains within a specified tolerance,
despite ovality of the pipe. Therefore, this project also investigates
on-line standoff estimation and control for this application.
Solidification cracking in high strength cellulosic weld
metal
Solidification cracking of steels is composition and cooling
rate dependent and can occur in high strength steel weld metals
which are being used increasingly for strength matching of high
strength low alloy structural steels.
A Gleeble thermomechanical simulator has been used to investigate
the susceptibility of high strength cellulosic weld metals to
hot cracking. Four different kinds of commercially available
weld metals are being studied in the current research. A special
sample holder has been constructed in order to achieve cooling
rates similar to those experienced in girth welds of steel pipelines.
Samples of different weld metals have been heated above the
melting point and cooled at different rates. Optical microscopy
has been employed to characterise hot cracking of weld metals
and to provide guidelines for the conditions under which hot
cracking is possible under actual welding conditions.
Fracture risk in pipeline girth welds
The critical assessment of the significance of defects within
a pipeline girth weld has cost implications on the production,
repair, and inspection of pipelines during construction. Current
standards may be too conservative and too demanding with the
consequence that benign defects are repaired. This is a significant
economic penalty.
Wide plate tension tests have become an acceptable way of establishing
the maximum defect length that can be tolerated for a given
welding procedure and pipe material combination. This is based
on a safe condition being one that promotes plastic deformation
within the pipe material before the weld yields. However these
tests are difficult to carry out and can cover relatively few
weld conditions. In addition there have been relatively few
fracture tests on full-scale pipes, so the relationships between
plastic behaviour in the wide plate tension test and behaviour
of the pipe under service loads is not well established.
This project work is attempting to address this topic by analysis
of such plastic behaviour using numerical non-linear, elastic-plastic
finite element methods. Simply, numerical models of wide plate
tension tests are being compared with similar numerical models
of defects in full-size, pipeline girth-welds subjected to simulated
in-service loading.
Currently models of wide plate tension tests have been developed
and the predicted behaviour compared against test data. The
development of full-size pipe models is in progress.
Defect acceptance levels in high strength pipeline girth
welds
Previous research on this subject by the Centre has addressed
the critical issues affecting defect acceptance levels in high
strength pipeline girth welds and there is now evidence to support
extension of the current generalised fitness for purpose based
defect acceptance level in Australian Standard AS2885.2. This
has the potential to increase the economic benefits to a larger
number of pipeline construction projects by avoiding unnecessary
repairs and costly cut-outs. However, the work also identified
that current cellulosic consumables can considerably undermatch
both X70 and X80 grade pipe and that conventional workmanship
standards may not be appropriate for thin walled high strength
pipelines. These projects have developed the expertise and the
appropriate experimental techniques to determine appropriate
workmanship defect acceptance limits for the pipeline industry
for the safe and economic operation of petroleum pipelines in
Australia.
Pipeline hydrostatic testing
Mathematical models have been developed to gain a more fundamental
understanding of pressure/temperature relationships in buried
pipelines during hydrostatic leak testing for Australian gas
pipeline conditions. Fibre-optic methods are being developed
for pipeline leak testing.
Recommendations have been made for temperature stabilisation
criteria, after the test section has been filled and pressurised,
as a function of test water temperature, ground temperature
and ambient temperature. Additionally, recommendations have
been made for methods of temperature measurement of buried pipelines
to allow correlation with pressure changes.
The mathematical modelling should shortly be completed and
field trials are planned for the fibre-optic instrumentation.
Pipeline resistance to external interference
External or mechanical interference is the major cause of failure
of onshore pipelines. The latest edition of the Australian Standard
for gas and liquid petroleum pipelines AS2885.1-1997 includes
the requirement to prove sufficient resistance to external penetration
using risk assessment techniques. However, at present there
are limited experimental and analytical data on the consequences
of external interference. The aim of this project is to generate
guidance on the probable damage resulting from typical external
interference threats on Australian gas pipelines. Work to date
has concentrated on collecting available literature on experimental
studies of pipeline denting, gouging and puncture, as well as
data on mechanical equipment types and sizes in Australia.
Stress in girth welds
This project is addressed to the solution of residual stresses
during the combined processes of root-pass welding, lifting
and lowering and hot capping. Non-linear, elastic plastic thermal-mechanical
models will be used. This stress development is expected to
have an important influence on hydrogen cracking.
Weld repair in gas pipelines
Advanced numerical 3-D models will be used to directly calculate
the possibility of cracking or burn through during weld repair.
The systematic use of weld sequence will be used to optimise
a temper-bead technique for the control of post-weld hardness.
Pipeline awareness
A literature survey will be conducted and a database developed
of procedural methods used to inform people of the location
of pipelines and of the serious consequences of damage. Sociological
techniques will be used to measure the effectiveness of these
methods.
Pipeline backfill specifications
The specifications will be reviewed and a set of specifications
will be developed that will meet the need of pipeline designers
and operators taking into account all soil and rock types that
may be encountered on pipeline routes.
|